Hope Hollow Road will get safety improvements including wider shoulders from Plantation Run Drive to Hope Hollow Lane and an intersection upgrade at Hope Hollow Lane. Gary’s Grading and Pipeline Inc. was the lowest of 11 bidders at $1.02 million for the nine-month project.
The Dickerson Group Inc., was the lowest responsive bidder out of 13 bids received for two other safety projects.
One will improve the intersection of Pate Road and Old Loganville Road by adding turn lanes at the i 072109_DOT_SPLOSTprojects.docntersection and at the entrances to nearby neighborhoods. The bid was just under $818,000 for the nine-month project.
Dickerson will also extend sidewalks on Bethany Church Road from SR-124 to the Centerville Library. The four-month, $310,000 project will provide a continuous pedestrian connection from Shiloh High School to State Route 124.